This combined cycle power plant consisting of two single shaft combined cycle units with main equipment 2 x (9FB+A16) supplied by General Electric.
A major inspection performed on a General Electric steam turbine model A16. In this project, low-pressure and high-pressure turbine cases are taken, coupling between generator and steam turbine detached and HP rotor and LP rotor removed as well. All diaphragms are removed. Each removed part checked by according to the GE standards. This is the first phase of the outage.